About Project
Consultant Groups and Contractors
The MRT Orange Line (east) “Thailand Cultural Center – Min Buri” has consultants and contractors as follows:
1. Project Implementation Consultant (PIC)
Assist the MRTA in supporting the project. The construction of civil works and the operation of the system (which is under consideration of MRTA for proceeding), led by MHPM Co., Ltd and three other companies.
2. Project Management and Construction Supervision Consultant 1 (PMCSC1)
To manage and control the construction of civil works of the contract, which is Contract E1, Contract E4 and Contract E5, led by Chotichinda Consultants Co., Ltd. and 3 other companies.
3. Project Management and Construction Supervision Consultant 2 (PMCSC2)
To manage and control the construction of civil works in the contract, which is Contract E2, Contract E3 and Contract E6, led by MAA Consultant Co., Ltd. and 5 other companies.
4. Contract E1 : CKST Joint Venture consists of CH. Karnchang Public Company Limited and Sino-Thai Engineering and Construction Public Company Limited.
Responsible for design and construction of tunnels and underground stations from Thailand Cultural Centre - Ramkhamhaeng 12 distance of about 6.29 km, there are 3 MRT stations.
5. Contract E2 : CKST Joint Venture, consists of CH. Karnchang Public Company Limited and Sino-Thai Engineering and Construction Public Company Limited.
Responsible for the design and construction of tunnels and underground stations from Ramkhamhaeng 12 - Ramkhamhaeng 34 distance of about 3.44 km. There are 4 MRT stations.
6. Contract E3 : Italian-Thai Development Public Company Limited.
Responsible for design and construction of tunnels and underground stations from Ramkhamhaeng 34 - Khlong Ban Ma instance of about 4.04 km. There are 3 MRT stations.
7. Contract E4 : Unique Engineering and Construction Public Company Limited.
Responsible for the construction of viaducts and elevated stations. It is about 8.80 km from Khlong Ban Ma - Yaek Rom Klao. There are 7 elevated stations.
8. Contract E5 : CKST Joint Venture, consists of CH. Karnchang Public Company Limited and Sino-Thai Engineering and Construction Public Company Limited.
Responsible for construction of depot which consists of a operation and maintenance center with other buildings at MRTA area and adjacent to existing depot.
9. Contract E6 : Unique Engineering and Construction Public Company Limited.
Responsible for design and construction of track works system for the whole project.
Contract E1 to Contract E6 has commenced on 2 May 2017 and has a term of contract of 1,980 days, which will end up on October 2, 2022.